Veritas will supply fully-trained installation engineers to assemble and install all room modules.
Installation supervisor inspection
Room is laid out & verified with general contractor
Verification of height clearances, piping, electrical, HVAC runs
First course of block laid in mortar bed
Multiple wythes of block are placed to achieve required wall thickness
VeriShield block are dry stacked in a running bond pattern

Steel reinforcing bars are placed in 5” x 5” horizontal and vertical bond beams
Frequency of bond beams is determined by project location and seismic conditions
Electrical conduits placed outside wall barrier
Dosimetry access conduit is placed into the Veritas wall
Door frame is installed at door opening
Top of walls are set with a horizontal bond beam with steel bearing plates
Steel beams are placed directly on top of and are welded to steel bearing plates
Ceiling shielding is placed directly on top of steel beams
Cable passageways, duct location and piping are coordinated
Duct shielding is placed beneath HVAC penetrations
Door is installed by our team of experts with your choice of door finishes
Interior of the room is completed with your choice of Veritas Modular panels or stud and drywall system